New Rowing Club a Model for Advanced Pile Foundation Technology

We recently spoke with Matthew Conte, of Conte Company, about a foundation project they completed for a 2-story rowing club in Norwalk Harbor. Rowing clubs often prove especially difficult to build due to their proximity to the water, and the ground on which they are built. Building near or above water brings its own set of challenges for pile foundation technology, along with strict guidelines to which builders have to adhere.

In the case of this building, the ground floor of the rowing club is to be used for storage of the boats and equipment, while the upper floors are used for meetings, offices and social areas. Crew has always been a mainstay in the Connecticut area and rowing clubs are an important piece in the community, serving as both an athletic and social gathering place. Matt and his team were eager to finished this project quickly and efficiently, in order to get the general construction started on the 6,000 sqft, pre-fab, metal butler building, so it will be ready for the upcoming season.

In order to build this rowing club, Conte Company installed 56 27′ Drivecast piles. They tied those piles to a grade beam grid, on which a heavy slab of concrete was poured. The soil conditions, which were waterlogged every time the tide came in and composed of organics, fill and silty material, were not suitable for traditional building. The engineering team ultimately determined that there were only a few cost-effective pile foundation technology options for a site plan like this. The only other alternatives to Drivecast were helical piles, or H-Piles.

According to calculations and field tests, utilizing helicals would have maxed out at around 40-50 kips (1 kip = 1,000 pounds of force), whereas each Drivecast pile supported a staggering 120 kips! Matt explained to me that the other alternative, using H-Piles, would require pile lengths of up to 75ft in length, and would’ve taken significantly longer to install. For starters, H-Piles typically come in 50 foot lengths, so each pile would need to be spiced together to produce the full 75′. What’s more, when you’re talking about driving piles of this enormous length, you need some enormous equipment to do the job. In this case? A massive crane would be needed to drive each of the H-Piles deep, deep into the earth. By contrast, Conte Company’s Drivecast piles only required a 14 ton excavator to get the job done. Matt explains it best:

“A 14-ton Ex looks like a toy, sitting next to a crane like that. We pulled up our machine on a trailer and were in-and-out of the job site quickly.”

Matt and his team installed all of their Drivecast piles within 5 days; start to finish, and had no issues installing them. The grouted columns were allowed to dry for 5 days before testing, and again had no issues, even in the salty, waterlogged silt. As an added bonus, the site was located on property owned by a chemical plant, regulations for which are far more stringent than other environmentally regulated industries. Again, no worries, Conte Company sailed through all requirements with ease. The entire project went off without a hitch.

The building Matt and his team recently built is located on Norwalk Harbor, and will be a great addition to the community. Matt and his team, along with the revolutionary pile foundation technology called Drivecast from Hubbell-Chance, allowed this project to be done faster and cheaper with less work, and smaller equipment than H-piles or helical piles.

What more do you need? Download the official Drivecast brochure below:

Download Now

Matt Conte to Speak at DFI SuperPile ’18 Conference in New York

Matt Conte, Principal at Conte Company and Jim Davis, Project Engineer at GZA will be speaking at this year’s DFI SuperPile ’18 Piling Design & Construction Conference to discuss emerging pile technologies and the future of geotechnical engineering. The two will delve into results from a recent test of the new Hubbell-Chance® Drivecast® Displacement Pile, which promises to upend the deep foundation industry. This presentation will take place on Friday at 12pm.

View Conference Details & Buy Tickets

Please join us for the biggest piling design and construction conference of the year.

Why is Structural Load Testing Important for Foundations?

Load testing services by Conte Company

Load testing, when performed professionally, can help a contractor meet complex code requirements. By confirming certain calculations and providing additional information about the deep foundation plan, a well-performed load test is essential to ensure that the foundation is strong enough to pass all structural requirements and inspections.

Load Testing 101

A load test is performed by applying pressure to a specific pile in predetermined directions; either by compression (push), tension (pull), or laterally. The load is generally applied via a hydraulic jack to make sure the pressure is equal to the final load requirement. A reaction frame is then applied against the hydraulic jack. Once activated, any movement of the pile or the test apparatus is monitored and logged, and the results are used to determine the capacity of the pile being tested.

Load testing in a confined space

Load Testing Accessibility

One of the main challenges to safe load testing is having enough space for the reaction beam and other equipment. Whether it’s inside a building, twenty feet below grade or someplace with limited access to utilities, Conte Company can perform challenging load tests accurately and safely. With our custom-designed reaction beam, we’ll get everything in place with no surprises and test to over 200 kips.

As you can see in the job below, load testing was pretty tight at this natural gas substation, where caution, safety and accurate load test results were an absolute MUST, which is why they hired Conte Company.

Load Testing Services from Conte Company

Conte Company has the engineering experience and the required tools to perform geotechnical load tests on a variety of deep foundation systems. We’ve done hundreds of load tests on everything from micropiles and helical piles, to augercast, vibro stone columns and aggregate pier systems. While we do provide deep foundation installation services as well, many of our load testing clients come to us for accurate, unbiased, 3rd party data.

Our tests are performed following ASTM, D1143, D36889 and D3966.

need Reliable load testing?

Call Conte Company for a quick evaluation.

 

Load testing at a natural gas substation

Introducing Drivecast™ The Next Generation of Pile Foundation 

Introducing Drivecast - A Revolutionary Screw Displacement Pile for Stronger Foundations

Drivecast™ is a highly innovative anchoring solution which can provide tremendous support for heavy loads. This brand-new technology uses a unique soil displacement methodology to advance a pile into the ground via rotation. Each pile section consists of a centralized shaft made of structural steel, while displacement assemblies are attached at regular intervals from the head.

Conte Company helped Hubbell-Chance® with the design and development of this revolutionary new pile, and the end result is unlike any other deep foundation system we’ve ever seen before. By coupling the simplicity of helical piles with the stability of displacement piles, we’ve come up with a better solution for some of the trickiest deep foundation projects.

Advantages of the Drivecast System

There are a number of advantages offered by the Drivecast system which make it very appealing from the standpoint of being cost-effective, being better adapted to specialized site requirements, and for providing maximum support as an anchoring solution.

  • higher capacity, smaller steel components
  • 3.5″ pipe shaft tested to provide over 100 tons
  • can be extended by simple bolted joint connections
  • grouted shaft offers corrosion resistance
  • increased buckling and lateral strength with larger grout shafts
  • proven to achieve higher capacities with shorter lengths
  • installation is less expensive because it can be accomplished by smaller crews
  • drilling costs less than Augercast but is more productive
  • no pre-drilling is necessary
  • there are no spoils, and no expensive trucking of spoil material off-site
  • ideal for usage in low-access, low-clearance situations
  • requires smaller, non-specialized equipment
  • minimal site disturbance and vibration

When you have limited access, Drivecast is a great solution

Because it can be installed using only small, standardized equipment, it can be used in areas which have limited access and clearance, and there is virtually no vibration or spoils which result from the process. Only a small crew is necessary to fully implement the Drivecast screw displacement pile, and this adds to its appeal as a system which offers minimal site disturbance. Its ease of installation coupled with high-performance anchoring, make this the most exciting pile installation product to come along in recent years.

Already, Drivecast screw displacement piles have been shown to be very effective in such applications as:

  • new construction
  • heavy highway projects
  • commercial or industrial buildings
  • bridges and abutments
  • sports field lighting
  • seawalls and secant walls
  • pipelines, sewers, and tank reservoirs
  • mid-rise foundations
  • highway lighting
  • underpinning

Whenever greater capacity might be required on a project, or where soil quality makes reliability an absolute must, Drivecast screw displacement piles will provide the optimal solution.

How it Works

The pile itself is advanced into the soil by downward pressure, at a rotation speed of between 5 and 20 RPMs, with both pressure and rotation levels determined by the character of the soil encountered at a drilling site. As the hydraulic drive-head progresses, and successive pile extensions are installed, a cylindrical void is created, into which gravity-fed cement grout is poured.

The grout is maintained in a surface-level reservoir and is prepared at the time of drilling. Drivecast piles are thus implemented in sections until the desired depth has been achieved. The result is a stable, high capacity, grouted displacement pile, with a steel core capable of anchoring virtually any kind of foundation.

Versatility of Application

Drivecast screw displacement pile installation is especially well adapted for situations where increased capacity is indicated, or in corrosive environments threaten deterioration of the piles. Because the gravity-fed cement grout surrounds the bore shaft as drilling occurs, a first level of protection is provided, and if soil conditions are particularly corrosive, a hot-dip galvanized coating can be applied to establish a second line of defense against corrosion. Due to its usage of smaller, standardized equipment, it has a very compact installation process, making it ideal for sites where there might be low clearance, low overhead conditions, or restrictions on site disturbance.

Want more Information?

Download the Official Drivecast™ Brochure

Watch the video of Drivecast™ in Action:

Don’t Delay Construction Until Spring: Helical Pile Foundations can be Installed in the Dead of Winter

civil engineers at construction site plan on installing pile foundations in Winter

These days, there’s really no reason to wait through the entire frozen season before starting that major construction project you’ve been thinking about. The deep freeze which has held much of the U.S. in its grip this January might be a deterrent to building in some respects, but it certainly should not prevent you from installing pile foundations in winter, especially if you intend to use helical piles. When helical piles are being used, there’s simply no need to wait for the ground to thaw out – they can be installed in most frozen ground.

Installing Pile Foundations in Winter

Admittedly, there can be an added expense to winter installation of foundations, particularly if really frozen conditions prevail. Like almost every other outdoor pursuit in the dead of winter, there are special considerations necessary, which translate to a slightly higher cost for helical piles. For instance, in those cases where the ground is frozen solid, a more powerful pile might be needed to penetrate the frozen soil, after which it would be replaced with a ‘production pile’ for the actual foundation.

In really cold weather, it may also be necessary to keep concrete grout mixture warm for a period of time, after mixing and before it is placed in the ground. For this process, heaters have to be setup at the mixing site, and the concrete mixture must be entirely contained within this area prior to having it poured into the pile. While there would be some added expense associated with these measures, you can literally save months of construction time by installing pile foundations in winter, and not having to wait for favorable weather.

Pouring Concrete Foundations in Winter

It’s certainly possible to install concrete foundations in the winter, but some extra consideration is necessary for the whole process. For instance, the concrete supplier would have to mix the concrete with hot water, so it could survive the temperature drop when it comes in contact with the outdoor air.

Since it usually takes twice as long or longer for concrete to set in cold air, it might be necessary to use an accelerant in the mixture to speed up the setting process. It may also be necessary to install windbreaks or temporary enclosures, along with heating systems, to prevent the concrete from drying out too quickly, and to prevent sudden temperature drops from cracking the concrete before it has a chance to set.

Extra Installation Costs vs. Waiting Until Spring

If you really need to keep your building project on schedule, and don’t want to wait until a springtime thaw provides you with ideal conditions, you can definitely get your foundation in place during even the harshest winter conditions. And you can install a concrete foundation if you don’t mind all the added expense of winter excavation, warm concrete delivery, treatment with accelerants for fast setting, and all the protective measures that will be needed to maintain sufficient warmth for an extended period of curing.

The truth is, from almost every angle you look at it, employing helical piles offer significant advantages, especially in the winter. Even if you have your piles encased in grout, the concrete mixture settles below the frost line, where it can cure naturally without any artificial heat. And although larger structures typically require concrete slabs to be poured to complete the foundation, most of the foundational support lies well below surface, where temperatures are stable year round.

As always, there is far less disturbance to the surrounding area with helical piles, since they do not require any major excavation, and can be installed with much smaller equipment—this also allows for better accessibility for hard to reach areas. Installing pile foundations in winter can be done rapidly, and if there is ever a need to remove or replace them, that can be easily done.

Construction Doesn’t Need to be Seasonal

What would the financial cost be if you had to wait several months for warmer weather, before proceeding with your construction project? That doesn’t have to happen when you opt for installing helical piles during the winter months. With a cost that is only slightly higher, all the same terrific advantages can be realized by installing pile foundations in winter – with fewer worries about massive snow removal, properly curing concrete, or moving major pieces of equipment around on a construction site.

While everyone else is watching the snow fly and the ground freeze, you can be getting a foundation in place, and planning for all the other steps which follow afterward.

Ready to Start Thinking About Your Next Construction Project?

Talk to Conte Company. We can help you choose a stable, cost effective foundation for your next job.

Contact Us

Determining the Cost of Helical Piles

engineers costing helical piles at an industrial facility

There are a number of factors which go into determining the cost of helical piles. Some are more obvious than others, but in the end, the chances of getting an accurate estimate will be much more likely when an experienced installer weighs the following criteria.

Geographical location of the job site

One cost factor which you might find a bit surprising is the element of geographic location. In a cost survey conducted by Helical Pile World in 2016, it became apparent that costs for the same kind of helical pile project would have a significant variance based on which part of the country work was done. Generally speaking, the more expensive pricing was in the Northwest and Mid-Atlantic states, while the least expensive cost of helical piles was quoted by companies in the Midwest and Plains states. So, if you have a project where helical piles will be used, the first cost factor will depend on which region of the country your project will be located.

Repair or new construction

The second most important cost factor in this survey is the type of project to be built. Participating companies universally quoted higher prices for remedial projects involving helical piles, as opposed to new construction projects with pile work. In many cases, the new construction was only about half the cost of the repair work.

After these two top factors, the cost elements tend to be closely related to the actual foundation installation work, which involves the piles themselves. We have broken these factors down as follows.

Number of piles

The number of piles needed on a given project is only partially determined by the size and footprint of the structure to be supported. The amount of piles necessary is also greatly influenced by the loading requirements, support requirements, structure type, and building codes applied to the project.

More importantly, because helical piles come in different sizes at different price points, one hundred piles of one size can cost less than fifty of another. The estimating contractor and the project engineers must be highly experienced in being able to determine how many of each size helical pile will need to be used.

Type of piles

The type of helical piles being used can also vary in diameter, shape and style, as well as whether they are being installed with or without grout.

The shape of the piles is either a square shaft or round shafts. Common square piles come in 1.5”, 1.75”, 2”, 2.25” and up. The common pipe piles come in  2 7/8”, 3.5”, 4.5”, 5.5”, 6.5”, 8”, 10”, etc. Typically, the bigger the diameter of the pile shaft, the more costly they will be.

Grouted shafts are a relatively new development in helical piles. As an anchor is being screwed into the soil, a grout column is gravity fed all around the shaft to reduce the likelihood of buckling under high stress. Such a technique is commonly used in soft soils, and has the effect of making the whole column much more rigid, while increasing the load capacity of the foundation itself. Grouted piles do not cost significantly more than un-grouted shaft installations, but can significantly improve performance. In many cases, small grouted square shaft piles actually cost less than un-grouted pipe shaft piles with similar loading capacities.

Once again, the type of pile used is very project specific and the best pricing will be determined by an experience estimator.

Depth of pile installation

The depth of the pile installation will influence the cost of helical piles simply because it takes more time and material to install deeper, more secure foundations. In many cases, anchoring will need to be drilled deep enough to a point where a more competent layer of soil resides. The load-bearing requirements of the project will also affect how deep piles need to be anchored.

For example, a pile going 40′ deep will add more to the material cost of a job than one going only 20′ deep. More pile extensions need to be added to the main shaft in order to achieve the greater depth. Installing longer piles also increases the time that drill crews need to be on-site.

Soil conditions

The design and selection of the piles being used for a specific project is directly affected by the encountered soil conditions. Buckling, liquefaction, density of the bearing layer to be penetrated, and density of the upper fill layers, all play a factor in which pile is chosen and the overall cost of the job.

In short, the soil conditions for a project will play a large part in determining the number, type, size and depth of piles to be used. As explained above, the choice of helical pile has a significant affect on the cost of helical piles material, needed for the project.

Cost of helical piles – The bottom line

Like all construction, estimated bids are subject to unforeseen developments. However, when an experienced contractor/installer/estimator work up an estimate for a specific installation of helical piles, and take into account ALL of the above considerations, you can be confident that the estimate you receive is realistic and accurate. Location, type of job (new construction or repair), the number, type, and depth of pile installations and the type of soil are all important factors. They, in combination, will determine your price and why only an experienced helical pile installer will be able to deliver a reasonably accurate figure for your project.

Need a quote on a helical pile job?

Request a Bid from Conte Company

or contact us

How a Helical Pile Foundation Can Speed Up Your Construction Project

A helical pile foundation can lead to faster construction and less down-time

Not many construction projects have the luxury of an open-ended time frame for completion, and in fact most projects have an understandably tight schedule which has to be observed. In construction, as in virtually all businesses, time is money, and this is especially true when all other tradesmen and contractors are waiting for the foundation of a structure to be installed. In many cases, a helical pile foundation can greatly reduce the time-to-build.

At most times in the past, there was literally no choice but to wait for a concrete foundation to be excavated, poured, and to dry before all other tasks associated with building construction could get underway. However, that model is changing more and more these days, as the advantages of a helical pile foundation become more universally known and understood.

When are Helical Piers Faster?

First and foremost, helical foundations are almost always installed more quickly than other piling methods such as caissons or driven piles.  While some common applications include support for bridges, boardwalks and industrial piping, engineers are constantly coming up with new ways to use helical piles as a time-saving alternative. Particularly useful for construction in wetland or flood-prone area, replacing a concrete foundation with helical piles can shave weeks and even months off a project.

One of the biggest advantages, especially for light industrial, temporary or above-ground structures, is the speed at which a foundation can be installed using helical piles.

How do Helical Piles Save Time?

Right from the very first step, helical piles save valuable time in the implementation of a foundation. No large excavating equipment is needed for the installation of the piles themselves, so as soon as engineers have tested the soil to determine the degree of anchoring which will be needed. A helical pile foundation can be screwed directly into the ground with machine-mounted hydraulics or machinery fitted with electrical drilling equipment. Almost any type of soil or ground is suitable for helical piles, other than bedrock itself, so virtually all locations are acceptable.

An aspect of helical pile installation which shouldn’t be overlooked is the actual installation itself. As piles are being augured into the ground, the rotation rate ranges anywhere from 6 to 10 rpm, which allows progress to proceed at roughly 2 feet per minute. That means that an anchoring requirement going 50 feet deep could be completed in less than an hour. Once all piles are in place, they can be used for load-bearing immediately, as opposed to having to wait up to a month for concrete to be cured, or grout to become dry.

At the end of installation, there’s also no major cleanup to be done, as there might be with any other kind of foundation installation. Installing helical piles is a very clean operation, which minimally impacts the surrounding environment, and does not require that excess soil be carted away in trucks to some other location. This itself saves an entire step which would be necessary in a major excavation, which in turn reduces the overall time needed to complete the foundation.

How do Helical Piles Keep Costs Down?

The bottom line is that when helical piers are used to anchor a new structure, there is no waiting for other construction processes to begin. Unless concrete footings or grade beams need to be poured, other aspects of construction can begin on the same day that piers have been secured. It would be hard to over-estimate the impact this can have on any kind of new construction project, since so much time is saved by the speed of installation, and the immediate readiness for subsequent contracting tasks.

Keeping costs down on a construction project can be the difference-maker on how profitable it is, and one of the most important ways that costs can be effectively managed is by reducing the overall time frame necessary for completion. There are several other very important advantages to adopting the installation of a helical piers over some other process for foundation installation, but when you’re thinking about your project’s bottom line, speed is one of the most compelling reasons.

 

Ready to speed up your next project? Talk to Conte

 

Building in a Flood Zone: 5 Tips for Hurricane Construction

Building in a Flood Zone - Tips for Hurricane Construction

When the weather turns downright dangerous, like it did with recent Hurricanes Harvey and Irma, saving lives is the number one priority. But when the wind finally calms, the rain finally stops and the skies turn blue, we look at property damage to evaluate how bad a storm really was. Victims of lost homes and other property damage need to know how to repair the devastation left behind and how to prepare for building in a flood zone in the future.

You’ll find our list of tips for hurricane construction below, but first, we want to show you why we feel so passionately about preparing for hurricanes and flooding through proper construction techniques.

We talked to Matt Conte, our 3rd generation owner of Conte Company, who understands that storm repairs are about more than just fixing houses. It’s about coming together as a community to help put people’s lives back together and get things back to normal. As we keep those in Houston and Florida in our hearts and minds during the devastating aftermath of Hurricanes Harvey and Irma; and as we prepare ourselves for a less ferocious Hurricane Jose in the Northeast, we can’t help but think back to two storms that ravaged our own community, just a few years ago…

The two storms that changed the way we think about coastal construction in New England…

Hurricane Irene was the storm that hit the East Coast of the United States during late August 2011 and ranks as the eighth-costliest hurricane in United States history. Here in CT, Irene dropped a devastating amount of rainfall, washing away roads, bridges and anything else in the flooding rivers’ path. Some major highways were closed for days and more than half the state lost power. But Irene couldn’t compare to Sandy, which arrived a year later. 

Hurricane Sandy (a.k.a. “Superstorm Sandy“) was the second-costliest hurricane in U.S. history, affecting 24 states, including the entire eastern seaboard from Florida to Maine. New Jersey, New York and Connecticut were hit particularly hard. All said and done, damage in the United States amounted to $71.4 billion.

Sandy completely destroyed thousands of Northeastern shoreline homes, and in some cases leveled entire neighborhoods. In cities that were completely unprepared for such an event, streets, tunnels and subway lines were flooded and made transportation impossible in one of the most populous metropolitan areas in the world.

“At Conte Company, we remember all too well the damage that these two storms inflicted. We were there in the days that followed, surveying the damage and helping people figure out what to do next. As one of the premier pile construction companies in the area, we had a unique perspective and a service that was suddenly in high demand.”

Helical pile foundations can help prevent hurricane damage

There were lucky ones too… But even many of homes with little damage needed to be raised to comply with new flood zone regulations and insurance requirements. In some areas, the flood line was raised by as much as two feet, which may not seem like a lot, but when it comes to flood-prone construction, every inch can make a difference.

Some were extra-un-lucky… Many houses were built on deep pile foundations and survived both storms, but many did not learn their lesson after the first one. Only one year after Irene’s massive clean-up effort began, Sandy barreled through and again destroyed some of the homes that were just rebuilt. In most cases though, those homes were built on the same types of foundations that failed the first time around.

“We felt just awful for people that had to rebuild and lift their homes twice in one year, but these homeowners went through even more hell when FEMA ran out of money after Sandy.”

Financing from FEMA decided whose houses were fixed and whose were not…

Immediately after Irene, FEMA money arrived quickly and homeowners poured all available funds into new construction. Conte Company helped many dig out and lift their homes quickly with new pile installations and the region recovered relatively quickly.

But the story was very different with Hurricane Sandy which pounded the East Coast just a year later. At first, FEMA was very responsive to Sandy. As long as a homeowner’s claim seemed legitimate, the money came through and people could hire contractors to rebuild and lift their homes. But soon, Sandy projects started taking an unusually long time to get financed… FEMA was simply running out of money. After two back-to-back, very deadly, very destructive hurricanes, they could not meet their financial commitments to ill-fated homeowners who were building in a flood zone.

For some, there was a government program called the Superstorm Sandy Relief Fund, which tried to help a few homeowners in the direst of straights. But today, many who did not qualify for this program have homes which still remain condemned, with “NO OCCUPANCY” stickers plastered to the front door.

Rebuilding homes that are literally and figuratively “underwater”…

When homeowners in this region did not receive the funds they expected, Conte Company knew they had to play a big part in the recovery process, for the sake of the community.

“In many of Connecticut’s beachfront areas, many homeowners were first wiped out by Irene, then by Sandy and then by FEMA’s dried up funding.”

Homeowners were holding onto properties with negative equity, and banks generally don’t refinance a home in that type of financial situation. Conte Company knew up front there wasn’t going to be a lot of money for repair, but felt duty-bound to help a community that has supported their business since the 1940s.

Conte Company took it upon themselves to work with a number of general contractors. Ones they knew could do the job the right way, make honest recommendations to homeowners and wanted to give a little back to a hurting community. They were able to lower their own subcontractor rates in order to assist these hand-picked GCs, who working hard for Sandy victims, to rebuild some homes, and help some people put their lives back together.

“In some cases, we lowered our pricing more than we should have, but if we didn’t, the competition would come in and do an inferior job. We couldn’t have that. We wanted them to be happy again. With the repair and with us. But mostly with their lives.”

Many people are back in their homes today because Conte Company was able to help them with costs after FEMA’s coffers were empty. Unfortunately, Conte couldn’t help everyone — there was just too much damage. Thousands of homeowners who were building in a flood zone had to abandon their properties completely, as the cost to rebuild was just too high.

Building in a Flood Zone: How to construct a home that will survive the storm…

To this day, Conte Company is often asked to check homes that were repaired after Sandy by less-than-qualified builders. Many of the issues they find are (or will cause) significant problems when the next hurricane comes roaring through. Some of these homes’ problems were simply never addressed, not necessarily because those builders were dishonest, but more likely because someone didn’t understand, or care, what the real problems actually were.

In the wake of the most recent superstorms to slam the U.S., there is no better time to discuss these issues which apply to both new and existing construction. As experts in the industry, we thought it makes sense to give people our best advice and recommendations for hurricane-proofing your new home, or repairing your old one.

The 5 Most Important Tips for Hurricane-Proof Home Construction

1. Hire a Reputable Structural Engineer

No project is ever the same and there is no one-size-fits-all solution. Trust your project engineer to make appropriate recommendations about your home’s foundation. Don’t have one you can trust? We work with plenty and are happy to refer you.

2. Lift Your Home Above the Floodline

Building in a flood zone can be somewhat nerve-racking for a homeowner, but you can greatly limit your potential for damage simply by making sure it’s out of the floodwater’s way. Most of the real damage is done by high waters and the pounding surf of wave action, not by high winds.

3. Use Helical Piles for Deep Foundation Support

As some of the most versatile pile types around, helical piles can be installed in just about any environment. When properly designed, helical piles can also provide:

  • excellent lateral load to resist winds in high-velocity zones
  • substantial uplift capacities to keep your house from floating away
  • exceptional scour support incase of soil erosion below your house
  • and here’s some more info on helical piles

4. Use Piles to Support Every Structure on the Property

Grade beams are a great way to connect all the piles for each structure to support the load with an interconnected system of foundations. Grade beams are installed below grade to create a solid foundation spanning from pile to pile. Every external structure should be connected, including the deck, garage, pool, stairs, patio, etc.

5. Don’t Cut Corners, Don’t Use Band-Aids

If you are building in a flood zone, remember one thing…

“Doing it once the right way, means you don’t have to do it twice later. Even if you do it cheap twice, it will end up being more expensive than doing it right the first time.”

Hurricane Damage?

Conte Company performs structural and site repairs like as underpinning, supports and responsible replacement of scoured material. Make sure the job is done right, so you don’t have to do it twice.

Call Conte Company Today

Construction Project Managers: How Do You Lighten the Workload?

construction-project-manager-workload

A construction project manager always needs to be in two places at once.

  1. In the office, planning the project and seeking out potential subs.
  2. And on-site, making sure the project is going well and that subs are doing the job right.

Has this ever happened to you?

“I need to work in the office today— no wait, there’s a problem, I gotta go to the job site.”

This dual responsibility may never go away completely. But by hiring the right employees and working with the best vendors, you can minimize problems on the job site and spend more time in the air conditioning.

Experienced Vendors Know What They’re Doing
(so you don’t have to babysit)

Finding a great subcontractor who can work autonomously, do their job quickly and efficiently is a construction project manager’s dream. Ensuring the result of all that meticulous planning often means being on the job site to field questions, check supplies and solve problems as they arise. Just imagine if all subs could be trusted to handle this kind of stuff on their own.

Being the Busiest Guy on the Job Site

As a construction project manager, it goes without saying that you have a lot on your plate. Maybe you build skyscrapers in busy cities, or help municipalities expand their airports or construct bulkheads at commercial marinas. Maybe you build luxury homes or shore up crumbling infrastructure on old college campuses. Whatever types of projects you work on, the workload and responsibility of a PM is more than just about anyone else involved.

On the construction site, you answer to your boss… and the client. You’re not the one hammering nails or guiding beams into place, but the buck will stop with you when it comes to staying under budget, on schedule and getting the job done right… all of which requires hiring the right subcontractors.

The responsibility of planning how and when the parts and pieces of a project come together takes some serious desk time. Endless phone calls, countless emails, erratic schedules, and constant research are a huge part of the job.

Wouldn’t it be nice if you had more time to do that stuff instead of spending so much time on the job site?

Hiring the Best, Getting the Best

While we can’t speak for everyone else, the experienced crew at Conte Company knows how to troubleshoot and solve problems on their own. We arrive at the job site on-time and ready to roll. We have our team assembled, safety gear on and everyone knows exactly what they’ll be doing that day.

As a small company, every crew we send out has a supervisor who’s worked in the industry for a decade or more. We manage our own supply chain, provide our own insurance, rarely come in over budget, and are always on schedule.

When you hire Conte Company to install your foundation, you can get out of the heat and back to the office to plan whatever comes next. Our long-time customers don’t worry about these things, because they know their job is in good hands. When you hire Conte Company, you don’t need to be in two places at once.

 

Conte Company is a family owned company since 1948. We are New England’s premier deep foundation contractor because we bring the best tools, equipment and crew to every job we take on. 

Learn about our Foundation Installation Services or Request a Consultation

 

Here are a few photos from our latest residential job in Fairfield, CT

Bulkhead Repair: Overcoming the Challenges of a Failing Boardwalk

Bulkhead repair in Norwalk Connecticut

Norwalk, CT is our home and the place where Conte Company was started in 1948. The town was founded in 1640 on the southern shoreline of CT known as the Long Island Sound. Norwalk is less than 50 miles from downtown Manhattan, but light years away in attitude and economic history.

Well known for its oystering industry, the town grew and prospered, attracting new residents who want to live on or near salt water while still in commutable distance from NYC. Charles Cove is a man-made tidal inlet, a quarter mile cut in from Long Island Sound, surrounded by a boardwalk, boasting luxury boat marinas and high-end condos. The Charles Cove Condos, which wrap cozily around the end of the cove, were built in 2004 and are highly popular for their location near beaches and shopping. Recent sales have them priced at just under a million dollars each.

Boardwalk foundations are a perfect fit for helical piles

Rotting Bulkheads in Need of Maintenance

Last year, the board of directors of the Charles Cove Condominium complex were informed that the wooden bulkheads holding up their complex were rotting and in serious danger of collapse. Apparently, the salt water tides running in and out of Charles Cove twice each day had taken a serious toll on the foundational structures. The residents, who strolled peacefully along the water on the complex’s walkways probably had no idea they were right on top of a disintegrating bulkhead.

Fortunately, someone did notice the rot and a marine contractor was quickly hired. But, instead of attempting a bulkhead repair by replacing the old bulkhead, the engineers proposed building a new bulkhead directly over the old one using new bulkhead sheeting, secured with piled tiebacks. This was going to be challenging, considering the natural elements in play, so the marine contractor wisely placed a phone call to Conte Company. (We are well known as the folks who love a good challenge and this one was going to be a doozy!)

Let’s talk about your project’s foundation challenges

A rotting bulkhead under a boardwalk in dire need of repair

Barging-In and Timing the Tides

We are well known for our helical pile technology expertise, which turned out to be the perfect solution to create tiebacks for this precariously threatened bulkhead.

We determined that our helical pile tiebacks would have to be securely drilled into the old timber retaining wall, a structure directly perpendicular to the salty waters of Charles Cove — and right below that 8-foot walkway. The new, poly-coated composite wall could then be attached to our secure helical piles. And, because this very tight working space was not accessible from land, we also planned to bring in a small barge to hold and transport our drilling equipment and crew for the bulkhead repair.

However, being raised in a shoreline town, we were aware in advance of a bigger challenge. Each 12.5 high tide was going to raise our working barge at least a few feet and once raised, we knew that our drilling boom would not always fit under the walkway. We would only be able to work from low-tide until just before mid-tide. Providing this critical timing information to the marine contractor in advance enabled them to plan ahead for other aspects of the project and helped to keep the project on schedule.

(we bend over backward to work efficiently)

Finding creative ways to repair a water damaged bulkhead under the boardwalk

Men Overboard (with Extensions)!

With the tidal problems addressed, our crack team anticipated, and solved, another watery problem before we began our bulkhead repair work. The barge, small as it was, still needed to be anchored 10 feet away from the bulkhead. The vertical piers that hold up the boardwalk kept the barge and our machines from getting up close and personal with our work. We were not going to get it close enough for our boom to reach where the piles needed to be drilled.

Our plan was simple, yet effective. We used standard pile extensions to lengthen our reach from the barge. Two crew members on the barge would load the extensions onto the helical piles. Two other Conte workers worked off a small floating dock where they could jump into the shallow waters, close to shore, and bolt the ends of the shaft extensions onto each helical pile as it was drilled into the wall.

At Conte Company we are team players and will to jump through hoops, or off barges, to get the job done right!

Ask us what we can do for your next foundation job

A few weeks later the job was done! Our men dried themselves off, the barge was floated out of Charles Cove and the residents began to stroll the walkways again. The customer, in this case, the condo’s board of directors, was confident that the bulkhead repair was completed according to the highest standards, as it passed all required inspections. Their residents were safe to once again stroll the walkways along Charles Cove and watch the sunsets —which are absolutely gorgeous over the waters of historic Norwalk, CT.

An aerial view of the Charles Cove boardwalk where our bulkhead repair project took place

How well are you vetting your contractors? Get Conte Company's 2017 Guide to Evaluating Geotechnical Contractors: 22 Mandatory Questions to Ask Before Getting a Bid.